Click the Exhibit button. An administrator has deployed a new virtual machine on an ESXi 5.x host. Users are complaining of poor performance on the application running on the virtual machine. Performance tools display the results shown in the exhibit. Which two tasks might improve the user experience? (Choose two.)

Click the Exhibit button.An administrator has deployed a new virtual machine on an ESXi 5.x host. Users are complaining of poor performance on the application...

Click the Exhibit button. 10 ESXi 5.x hosts will be installed as part of a vSphere 5.x deployment. Security hardening is required as part of the installation. The current security profile is displayed in the exhibit. Which three services shown in the exhibit are configured to run by default in a completed vSphere installation? (Choose three.)

Click the Exhibit button.10 ESXi 5.x hosts will be installed as part of a vSphere 5.x deployment. Security hardening is required as part of the installation....

A DRS cluster with two ESXi 5.x hosts is set to fully automated mode. One host in the cluster is running at 98% CPU utilization. The other host is running at 52% utilization. Upon analysis, it appears that none of the virtual machines are being migrated from the CPU-constrained host, and no recommendations are being generated. What are the two most likely causes of the problem? (Choose two.)

A DRS cluster with two ESXi 5.x hosts is set to fully automated mode. One host in the cluster is running at 98% CPU utilization. The other host is running...

An administrator is configuring an ESXi 5.x host with two dual-port Fibre Channel (FC) HBAs. The FC storage array has four active storage processor ports. Zoning is configured on both fabrics, with ESXi HBA ports and the array ports in the same zone. There are two LUNs with VMFS datastores configured. Using Round Robin multipathing, what is the maximum number of paths that can be used to send data to the VMFS datastores at any given time?

An administrator is configuring an ESXi 5.x host with two dual-port Fibre Channel (FC) HBAs. The FC storage array has four active storage processor...

vCenter Server is running in a virtual machine that is part of a vSphere DRS cluster. The vCenter Server virtual machine has been tested and can successfully migrate with vMotion between all ESXi hosts in the cluster. DRS is configured for partial automation. What happens if an ESXi 5.x host that is running the vCenter Server virtual machine experiences a power outage?

vCenter Server is running in a virtual machine that is part of a vSphere DRS cluster. The vCenter Server virtual machine has been tested and can successfully...

An administrator has just completed an update of an ESXi 5.x host. Prior to the upgrade, a backup of the host configuration was performed. After the upgrade, the backup was restored to the upgraded host. Shortly after the upgrade was completed, the administrator receives complaints that users are unable to power on virtual machines. What are the two most likely reasons that VMs cannot power up on this host? (Choose two.)

An administrator has just completed an update of an ESXi 5.x host. Prior to the upgrade, a backup of the host configuration was performed. After the...

Two child resource pools exist for a DRS cluster. The Production resource pool has been configured with a CPU reservation of 20GHA and a memory reservation of 20GB. The pool has 16 single-processor virtual machines and 4 dual- processor virtual machines. Each of these virtual machines has a CPU reservation of 1GHA and a memory reservation of 1GB. The Development resource pool and it's virtual machines have been configured with no reservations. The pool has 1 single-processor virtual machine and 1 dual-processor virtual machine. CPU Shares are set to 4000 and Memory Shares are set to 163840. The Production team members occasionally complain about the performance of their servers. Which two options could be part of the plan to resolve the issue while minimizing the amount of resources reserved by the pool? (Choose two.)

Two child resource pools exist for a DRS cluster.The Production resource pool has been configured with a CPU reservation of 20GHA and a memory reservation...

Click the Exhibit button. An administrator has deployed a two-node cluster with HA and DRS enabled. DRS has been configured for fully automated mode. The management and vMotion interfaces have been configured on separate physical networks. Initial DRS testing on this cluster reveals that virtual machines are not being migrated despite great disparity in resource use between the ESX hosts in the cluster. The exhibit shows the error and the network configuration for one of the hosts. Which task would successfully resolve this problem?

Click the Exhibit button.An administrator has deployed a two-node cluster with HA and DRS enabled. DRS has been configured for fully automated mode....

The storage administrator is preparing an action plan to upgrade a Fibre Channel storage array. The current plan will result in extended downtime for a VMFS LUN that is part of a SDRS cluster. What steps can be taken in a vSphere 5.x environment to minimize the impact of the downtime? (Choose two.)

The storage administrator is preparing an action plan to upgrade a Fibre Channel storage array.The current plan will result in extended downtime for...